You are the test manager on a project where system testing is being performed on software provided by a third party. You have received a complaint from the third party that the completeness of the defect data from your system testing is unacceptable.
Which of the following options could have been identified as missing from the defect reports sent to the third party?
Select TWO options.
A.
The project activity occurring when the problem was detected.
B.
Steps to reproduce the failure, along with the actual and expected results.
C.
The priority to fix the problem.
D.
The technical type of the defect.
E.
The software lifecycle phase in which the defect was detected.