FL-1.4.1 K2 Understand
Explain the different test activities and related tasks
A test process usually consists of the main groups of activities described below. Although many of these activities may appear to follow a logical sequence, they are often implemented iteratively or in parallel. These testing activities usually need to be tailored to the system and the project.
Test planning consists of defining the test objectives and then selecting an approach that best achieves the objectives within the constraints imposed by the overall context. Test planning is further explained in section 5.1.
Test monitoring and test control. Test monitoring involves the ongoing checking of all test activities and the comparison of actual progress against the plan. Test control involves taking the actions necessary to meet the test objectives. Test monitoring and test control are further explained in section 5.3.
Test analysis includes analyzing the test basis to identify testable features. Associated test conditions are defined and prioritized, taking the related risks and risk levels into account (see section 5.2). The test basis and the test object are also evaluated to identify defects they may contain and to assess their testability. Test analysis is often supported by the use of test techniques (see chapter 4). Test analysis answers the question “what to test?” in terms of measurable coverage criteria.
Test design includes elaborating the test conditions into test cases and other testware (e.g., test charters). This activity often involves the identification of coverage items, which serve as a guide to specify test case inputs. Test techniques (see chapter 4) can be used to support this activity. Test design also includes defining the test data requirements, designing the test environment and identifying the necessary infrastructure and tools. Test design answers the question “how to test?”.
Test implementation includes creating or acquiring the testware necessary for test execution (e.g., test data). Test cases can be organized into test procedures, which are often assembled into test suites. Manual and automated test scripts are created. Test procedures are prioritized and arranged within a test execution schedule for efficient test execution (see section 5.1.5). The test environment is built and verified to be set up correctly.
Test execution includes running the tests in accordance with the test execution schedule (test runs). Test execution may be manual or automated. Test execution can take many forms, including continuous testing or pair testing sessions. Actual test results are compared with the expected results. The test results are logged. Anomalies are analyzed to identify their likely causes. This analysis allows us to report the anomalies based on the failures observed (see section 5.5).
Test completion usually occurs at project milestones (e.g., release, end of iteration, test level completion). For any unresolved defects, change requests or product backlog items are created. Any testware that may be useful in the future is identified and archived or handed over to the appropriate teams. The test environment is shut down to an agreed state. The test activities are analyzed to identify lessons learned and improvements for future iterations, releases, or projects (see section 2.1.6). A test completion report is created and communicated to the stakeholders.
The learning objectives explained by the sections found for this search, in the same order.
Explain the different test activities and related tasks
None of the sections found for this search explains a learning objective.
No learning objectives match the current filters.
Business outcomes whose code or wording matches your search, with the learning objectives linked to each.
No business outcome matches this search.
No business outcomes match the current filters.
Keywords that the syllabi list at the start of a chapter — ISTQB Glossary keywords and domain-specific keywords — matching your search. Definitions are the ISTQB Glossary's.
No chapter keyword matches this search.
No keywords match the current filters.
Questions from the published sample exams that match your search — in the question, its answer options, or the objective or keyword it tests.
You work in a team that develops a mobile application for food ordering. In the current iteration the team decided to implement the payment functionality. Which of the following activities is a part of test analysis?
Which test activity involves working with test data requirements, test conditions, test environment requirements and test cases?
Which of the following test activities are MOST likely to involve the application of boundary value analysis and equivalence partitioning?
Given the following test tasks: 1. Derive test cases from test conditions 2. Identify reusable testware 3. Organize test cases into test procedures 4. Evaluate the test basis and the test object And the following test activities: - A. Test analysis - B. Test…
No sample exam question matches this search.
No exam questions match the current filters.